South Acton Regeneration – Carisbrooke Court Demolition Update
11 November 2024
Dear Neighbour
South Acton Regeneration – Carisbrooke Court Demolition update
As part of our ongoing commitment to keep our neighbours updated on the Acton Gardens development site and how works may impact you, we have updated the schedule of works below.
Stages |
Tasks |
Start/End |
Status |
Preparation of Carisbrooke Court for Demolition |
Erecting Hoarding Disconnecting services to the building Erecting scaffolding and Monarflex sheeting around building. |
5 August 2024 – 25 August 2024 |
Completed |
Soft strip Demolition |
Removal of all non- structural elements and fixtures of the building. Asbestos removal |
7 October 2024 – 1 November 2024 |
Completed |
Structural Demolition |
Demolition of the building’s superstructure. |
11 November 2024 – 7 February 2024 |
In Progress |
Substructure & Hard standing. Demolition Completion |
Vegetation removal Removal of hard standing and buildings foundations Demolition Completion |
10 February 2024 – 21 February 2024 |
Not Commenced |
As you can see from the programme above, the preparation of the site and soft strip has now completed. The structural demolition of Carisbrooke Court is to take place from 11 November 2024 and is estimated to take 16 weeks to complete.
Minimising Impact of Demolition on Local Residents
We have been working closely with the demolition contractor over the past few months to ensure that the impact of the demolition works on residents is minimised.
Through communication with residents at Acton Gardens and its neighbours, we appreciate that there are concerns in relation to noise, vibration, and dust. The demolition contractor will be monitoring noise and vibration levels throughout the demolition works to ensure they remain within agreed levels. Additionally, dust suppression equipment will be in operation during the demolition works, including the use of Monarflex. These dust precautions have recently been successfully used for the demolition of Frampton Court and Jerome Tower, effectively reducing the spread of dust.
If you have any further questions relating to the above, please contact the email address given in the footer below. The email address will be monitored, and responses will be provided to all queries.
Yours faithfully,
Acton Gardens LLP