South Acton Regeneration – Carisbrooke Court Demolition Update

11 November 2024

Dear Neighbour

South Acton Regeneration – Carisbrooke Court Demolition update

As part of our ongoing commitment to keep our neighbours updated on the Acton Gardens development site and how works may impact you, we have updated the schedule of works below.


Stages

Tasks

Start/End

Status

Preparation of Carisbrooke Court for Demolition

Erecting Hoarding

Disconnecting services to the building

Erecting scaffolding and Monarflex sheeting around building.

5 August 2024 –

25 August 2024

Completed

Soft strip Demolition

Removal of all non- structural elements and fixtures of the building.

Asbestos removal

7 October 2024 –

1 November 2024

Completed

Structural Demolition

Demolition of the

building’s superstructure.

11 November 2024

– 7 February 2024

In Progress

Substructure & Hard standing.

Demolition Completion

Vegetation removal

Removal of hard standing and buildings foundations

Demolition Completion

10 February 2024 –

21 February 2024

Not Commenced


As you can see from the programme above, the preparation of the site and soft strip has now completed. The structural demolition of Carisbrooke Court is to take place from 11 November 2024 and is estimated to take 16 weeks to complete.

Minimising Impact of Demolition on Local Residents

We have been working closely with the demolition contractor over the past few months to ensure that the impact of the demolition works on residents is minimised.

Through communication with residents at Acton Gardens and its neighbours, we appreciate that there are concerns in relation to noise, vibration, and dust. The demolition contractor will be monitoring noise and vibration levels throughout the demolition works to ensure they remain within agreed levels. Additionally, dust suppression equipment will be in operation during the demolition works, including the use of Monarflex. These dust precautions have recently been successfully used for the demolition of Frampton Court and Jerome Tower, effectively reducing the spread of dust.

If you have any further questions relating to the above, please contact the email address given in the footer below. The email address will be monitored, and responses will be provided to all queries.

Yours faithfully,

Acton Gardens LLP

yoursouthacton@lqgroup.org.uk

Share:
We use cookies to personalize content and to analyze our traffic.
Top